<i>Jamuna Fertiliser Factory </i>
Production at the Jamuna Fertiliser Factory (JFF) at Tarakandi in Jamalpur was suspended again due to technical glitches.
The factory suspended its production at around 9:00pm on Sunday when a mechanical fault was detected at the boiler tube of its ammonia plant, JFF sources said.
When contacted yesterday, JFF Managing Director Mir Mozaffar Hossain told The Daily Star that they are trying sincerely to repair the fault as early as possible.
"We hope production would resume at the factory after six days," he said.
Earlier, the factory halted its urea production on June 3 to June 6 last following detection of technical glitches on its urea plant. Production had also been halted at the factory for 11 days from July 9 to July 20 last due to repairing works on its different plants.