Adani deal unfavourable

Transmitting Adani’s power to get costlier

The overall cost for transmitting electricity from the Adani power plant in Godda, Jharkhand is set to increase further as two projects meant for that end are eyeing cost and time revisions.

Environment Network calls for cancellation of Adani Power deal

The government signed the deal under conditions that hugely favour Adani Power at the cost of Bangladesh, says Bangladesh Environment Network

What Adani Group has to say

The Daily Star contacted Adani Group for clarifications on certain aspects of the PPA and we are publishing the emailed comment from the Adani Group headquarters in Ahmedabad in India ad verbatim.

March 12, 2023
March 12, 2023

Transmitting Adani’s power to get costlier

The overall cost for transmitting electricity from the Adani power plant in Godda, Jharkhand is set to increase further as two projects meant for that end are eyeing cost and time revisions.

March 2, 2023
March 2, 2023

Environment Network calls for cancellation of Adani Power deal

The government signed the deal under conditions that hugely favour Adani Power at the cost of Bangladesh, says Bangladesh Environment Network

February 28, 2023
February 28, 2023

What Adani Group has to say

The Daily Star contacted Adani Group for clarifications on certain aspects of the PPA and we are publishing the emailed comment from the Adani Group headquarters in Ahmedabad in India ad verbatim.