Back Page

Padma Bridge: 9th span installed

Star file photo

Around 1,350 metres of the much-hyped Padma Bridge is now visible with the installation of ninth span on the pillars no 34 and 35 yesterday.

The 150-metre span, weighing 3,140 tonnees, was installed at the Jajira point around 8:45 am, said deputy assistant engineer of Padma Bridge project Humayun Kabir.

Earlier, the span of the Pabma Bridge was taken to the Jajira point by the 3600 tonnes capacity floating crane Tian-E from the Mawa Kumarbhog Construction Ward, five kilometres away from the point on Wednesday but it could not be installed till Thursday afternoon due to poor navigability at the point.

The works of Padma Multipurpose Bridge became visible with the installation of 150-metre first span on the pillars no 37 and 38 on October 30, 2017. Later, the second, third, fourth and fifth spans were installed on the pillars 38-39, 39-40, and 40-41 respectively in 2018.

Besides, the F-1 span (super structure) was kept on the pillar no 4 and 5 at Mawa point due to the construction works of pillar no 6 and 7.

The construction work on the country's largest bridge started in December 2015.

The 6.15-kilometre bridge will have a total of 41 spans, each 150 metres long.

According to the engineers concerned, a total of 41 spans will be installed on 42 concrete pillars.

Comments

Padma Bridge: 9th span installed

Star file photo

Around 1,350 metres of the much-hyped Padma Bridge is now visible with the installation of ninth span on the pillars no 34 and 35 yesterday.

The 150-metre span, weighing 3,140 tonnees, was installed at the Jajira point around 8:45 am, said deputy assistant engineer of Padma Bridge project Humayun Kabir.

Earlier, the span of the Pabma Bridge was taken to the Jajira point by the 3600 tonnes capacity floating crane Tian-E from the Mawa Kumarbhog Construction Ward, five kilometres away from the point on Wednesday but it could not be installed till Thursday afternoon due to poor navigability at the point.

The works of Padma Multipurpose Bridge became visible with the installation of 150-metre first span on the pillars no 37 and 38 on October 30, 2017. Later, the second, third, fourth and fifth spans were installed on the pillars 38-39, 39-40, and 40-41 respectively in 2018.

Besides, the F-1 span (super structure) was kept on the pillar no 4 and 5 at Mawa point due to the construction works of pillar no 6 and 7.

The construction work on the country's largest bridge started in December 2015.

The 6.15-kilometre bridge will have a total of 41 spans, each 150 metres long.

According to the engineers concerned, a total of 41 spans will be installed on 42 concrete pillars.

Comments

চলতি মাসে আরও তাপপ্রবাহ ও ঘূর্ণিঝড়ের পূর্বাভাস

পূর্বাভাসে বলা হয়, এ মাসে বঙ্গোপসাগরে এক থেকে তিনটি লঘুচাপ সৃষ্টি হতে পারে, যার মধ্যে অন্তত এক থেকে দুটি নিম্নচাপ কিংবা ঘূর্ণিঝড়ে রূপ নিতে পারে।

এইমাত্র