Power plant

Contract for Sylhet 90 M.W. combined cycle power plant (2nd. Unit) construction work was signed between PDB and M/S Harbin Power Engineering co. (HPE) on 12.09.05 with completion date on 02.01.08.
It is learnt that HPE completed the execution work and started the trial run operation by early Aug.2008. But the unit could not be put into commercial operation till now even after more than two years of its contractual completion date in the scenario of severe power crisis prevailing in the country. Moreover, this is a gas run power plant and gas is available there.
On the other hand, Fenchuganj rental power of 50 MW capacity on the same premises, planned after Sylhet 90 MW power plant, has already come into operation and is supplying power to the national grid and making normal business.
This is how the power sector is being run!